Scrum Velocity: Do’s and Dont’s

 

Velocity is “The measure of how many points the team burns down in a given Sprint on average.” Velocity measures the amount of work a single team can be expected to complete during an iteration. When we refer to story points, we are referring to a unit of measurement that expresses the estimated effort required to implement that Product Backlog item. These story points are calibrated and decided on by the team.

Calculating velocity

Most often in Agile teams, story points or T-shirt sizes are used to estimate effort. If you use T-shirt sizes, your team will map those sizes to a numeric value for the purpose of calculating a team velocity. 

When your team begins running Sprints or iterations, they won’t be able to accurately determine velocity because they will have no historical basis on which to calculate an average number of points completed in a Sprint. In their very first Sprint, your team will make a rough guess as to how many items they can complete just to get started. Once a few Sprints have been completed, your team will have a good measure of their velocity, and they will use that number to determine which items to include in their Sprint Backlog. This should be easy to do if your team has a properly prioritized and estimated backlog to work from. As you will recall from the videos, this process is called backlog refinement.

Using velocity for good 

When interpreting velocity, it is important to keep a few things in mind. You may feel inclined to share velocity with members outside of your team or to use velocity as a performance or comparison metric. You may also feel inclined to use it to determine a projected delivery date. However, some Agile experts warn against these practices. Let’s discuss why. 

Do: Be careful when sharing velocity with external stakeholders

Velocity can be helpful for individuals outside of the Scrum team, but when sharing it with non-team members, be very careful. Since velocity is different for every team, a stakeholder may not have enough context to interpret it. Be sure to share relevant supporting materials to help add context. A good example of this is sharing the velocity with a corresponding date range and visualization that indicates trends over time. There may be dips and spikes in velocity that draw insights and encourage improvements in future projects. 

Don't: Use velocity as a performance metric

It is natural for individuals to want to quantify performance through data, but it can be detrimental for a team to feel that kind of pressure within their Sprints. There may be executives, sponsors, or stakeholders that want to use velocity as a performance metric, but this will only hurt the team by encouraging tactics like intimidation. If the team is worried about their velocity making it seem like they are underperforming, the team’s culture can become harmed as a result. 

Don't: Use velocity as a comparison metric

If you are leading a few different Scrum teams, you may be tempted to compare the two teams’ productivity based on their velocity. You may have the impulse to check which teams are completing the most story points per iteration. However, the weight of different story points is subjective because they are created by the team. One team may consider a story to be five points, but another team might consider it to be closer to three points. Therefore, judging productivity solely on velocity isn’t accurate or fair. Additionally, velocity is not a measure of value. One team’s velocity might differ from another team’s, but this variability is fine as long as both teams are delivering value to your stakeholders.

Do: proceed with caution when using velocity as a metric for project delivery date

Using velocity to estimate the delivery date of a project spanning numerous Sprints can be tricky. Velocity can be used as a pressure point by external stakeholders who want to set a date for their product launch. Velocity can also create false expectations and a harshly competitive culture when the team doesn’t hit the estimated dates. Projecting deliverable dates is harmful because it can take a team several Sprints to really understand what they are capable of delivering in each iteration. Also, if you map out too many dates in advance, you aren’t able to account for the changes and issues that will arise. Therefore, make sure you are being careful not to use the estimated delivery dates as commitments. 

.